Linear Facilities (2014-2025)

Scope of Work Project Description and Location Client Implementation Period

Comprehensive survey work, design and working documentation development

Relocation of the Ostrogozhsk-Lebedinsky GOK main gas pipeline

JSC Lebedinsky GOK

2021 – present

Development of design and cost estimation documentation

Relocation of PJSC Gazprom utilities for the project: Construction of the R-256 Chuysky Trakt highway

LLC RosInstalProekt

2023 - present

Design documentation development, construction and installation works

Construction of a gas consumption network at an industrial plant in Moscow

JSC Ochakovo

2022 - 2023

Design and survey works, construction and installation works

Reconstruction of the gas consumption network of an industrial plant in the Moscow Region

LLC Holcim (RUS) CM

2022 - 2023

Permits and approvals, design and survey works, state expertise

Technological connection of capital construction projects to gas distribution networks, Moscow Region

JSC Mosoblgaz

2014 - present

Development of design and cost estimation documentation

Construction and reconstruction of gas distribution networks in Moscow

JSC MOSGAZ

2019 - present

Development of design and cost estimation documentation

Relocation of PJSC Gazprom main gas pipeline for the Northern Bypass of Lobnya project

LLC VTM Dorproekt

2022 - 2023

Development of design and cost estimation documentation

Relocation of a high-pressure gas pipeline at the intersection with the planned R-254 Irtysh highway

LLC RosInstalProekt

2020 - 2021

Design documentation development

Relocation of a section of PJSC Gazprom main gas pipeline at the intersection with a 220 kV power line in the Oryol Region

LLC Kerama Marazzi

2020

Comprehensive survey work, design and working documentation development, field supervision

Off-site gas supply system for the CCGT-420 unit of Verkhnetagilskaya State District Power Plant, Sverdlovsk Region

JSC Inter RAO

2018 - 2019

Comprehensive survey work, design documentation development

Construction of Runway 3 at Sheremetyevo Airport. Relocation of main and distribution gas pipelines, Moscow Region

FSUE Administration of Civil Airports and Airfields

2014 - 2016

Design works for the relocation and rearrangement of oil, product, and main gas pipelines

Construction of the Central Ring Road (TsKAD). Startup Complex No. 3 and No. 5. Stage 2 construction and interchange No. 31

OJSC Soyuzdorproekt

2014 - 2015

Thermal Energy Facilities (2015-2025)

Project Name and Location Client Scope of Work Implementation Period

97 MW gas-fired hot water boiler plant for residential development

LLC Montazhsetstroy

Design documentation development

2024 – present

10 MW gas boiler plant with external gas pipeline for an aerated concrete block plant, Moscow

LLC FSK Development

Design documentation development

2023 – 2024

15 MW gas-fired hot water boiler plant with supply gas pipeline for a resort complex, Krasnodar Krai

JSC DZ MIMARLIK VE INSAAT ANONIM SIRKETI

Design documentation development

2023 – 2024

5.5 MW boiler plant technical retrofitting for an industrial facility, Moscow Region

LLC Scandipakk

Design documentation development, construction, installation, and commissioning

2023 - 2024

16 t/h gas steam boiler plant with external gas pipeline for an industrial enterprise, Zelenograd

LLC FSK Development

Design documentation development

2023

Gas-fired hot water boiler plant with supply gas pipeline in Sokolniki Park, Moscow

State Autonomous Institution Sokolniki Park, Moscow

Design and survey works, state expertise

2022

3.3 MW gas boiler plant with supply pipeline for an administrative office complex, Moscow

JSC KOSHELEV-PROJECT

Permits, structural surveys, design development, expertise, construction and commissioning

2021 - 2023

18 MW gas boiler plant for a public administrative complex, Moscow Region

Ministry of Construction of Moscow Region

Design documentation development

2020 - 2021

Technical retrofitting of a 6.5 t steam/h boiler plant for an industrial complex, Moscow Region

LLC GeoPak

Permits, working documentation development, expertise and surveys

2020 - 2021

Technical retrofitting of a 24 MW industrial boiler plant, Moscow

JSC Plastics Institute

Permits, surveys, working documentation development, expertise

2017 – 2018

Technical retrofitting of a 35.0 MW combined steam and hot water boiler plant, Moscow

JSC Salyut Gas Turbine Research and Production Center

Working documentation development, field supervision

2016 – 2019

10.5 MW hot water boiler plant for a residential complex, Moscow Region

LLC Centro-Stroy

Design and working documentation development, construction and installation works

2016 – 2017