| Scope of Work | Project Description and Location | Client | Implementation Period |
|---|---|---|---|
Comprehensive survey work, design and working documentation development |
Relocation of the Ostrogozhsk-Lebedinsky GOK main gas pipeline |
JSC Lebedinsky GOK |
2021 – present |
Development of design and cost estimation documentation |
Relocation of PJSC Gazprom utilities for the project: Construction of the R-256 Chuysky Trakt highway |
LLC RosInstalProekt |
2023 - present |
Design documentation development, construction and installation works |
Construction of a gas consumption network at an industrial plant in Moscow |
JSC Ochakovo |
2022 - 2023 |
Design and survey works, construction and installation works |
Reconstruction of the gas consumption network of an industrial plant in the Moscow Region |
LLC Holcim (RUS) CM |
2022 - 2023 |
Permits and approvals, design and survey works, state expertise |
Technological connection of capital construction projects to gas distribution networks, Moscow Region |
JSC Mosoblgaz |
2014 - present |
Development of design and cost estimation documentation |
Construction and reconstruction of gas distribution networks in Moscow |
JSC MOSGAZ |
2019 - present |
Development of design and cost estimation documentation |
Relocation of PJSC Gazprom main gas pipeline for the Northern Bypass of Lobnya project |
LLC VTM Dorproekt |
2022 - 2023 |
Development of design and cost estimation documentation |
Relocation of a high-pressure gas pipeline at the intersection with the planned R-254 Irtysh highway |
LLC RosInstalProekt |
2020 - 2021 |
Design documentation development |
Relocation of a section of PJSC Gazprom main gas pipeline at the intersection with a 220 kV power line in the Oryol Region |
LLC Kerama Marazzi |
2020 |
Comprehensive survey work, design and working documentation development, field supervision |
Off-site gas supply system for the CCGT-420 unit of Verkhnetagilskaya State District Power Plant, Sverdlovsk Region |
JSC Inter RAO |
2018 - 2019 |
Comprehensive survey work, design documentation development |
Construction of Runway 3 at Sheremetyevo Airport. Relocation of main and distribution gas pipelines, Moscow Region |
FSUE Administration of Civil Airports and Airfields |
2014 - 2016 |
Design works for the relocation and rearrangement of oil, product, and main gas pipelines |
Construction of the Central Ring Road (TsKAD). Startup Complex No. 3 and No. 5. Stage 2 construction and interchange No. 31 |
OJSC Soyuzdorproekt |
2014 - 2015 |
| Project Name and Location | Client | Scope of Work | Implementation Period |
|---|---|---|---|
97 MW gas-fired hot water boiler plant for residential development |
LLC Montazhsetstroy |
Design documentation development |
2024 – present |
10 MW gas boiler plant with external gas pipeline for an aerated concrete block plant, Moscow |
LLC FSK Development |
Design documentation development |
2023 – 2024 |
15 MW gas-fired hot water boiler plant with supply gas pipeline for a resort complex, Krasnodar Krai |
JSC DZ MIMARLIK VE INSAAT ANONIM SIRKETI |
Design documentation development |
2023 – 2024 |
5.5 MW boiler plant technical retrofitting for an industrial facility, Moscow Region |
LLC Scandipakk |
Design documentation development, construction, installation, and commissioning |
2023 - 2024 |
16 t/h gas steam boiler plant with external gas pipeline for an industrial enterprise, Zelenograd |
LLC FSK Development |
Design documentation development |
2023 |
Gas-fired hot water boiler plant with supply gas pipeline in Sokolniki Park, Moscow |
State Autonomous Institution Sokolniki Park, Moscow |
Design and survey works, state expertise |
2022 |
3.3 MW gas boiler plant with supply pipeline for an administrative office complex, Moscow |
JSC KOSHELEV-PROJECT |
Permits, structural surveys, design development, expertise, construction and commissioning |
2021 - 2023 |
18 MW gas boiler plant for a public administrative complex, Moscow Region |
Ministry of Construction of Moscow Region |
Design documentation development |
2020 - 2021 |
Technical retrofitting of a 6.5 t steam/h boiler plant for an industrial complex, Moscow Region |
LLC GeoPak |
Permits, working documentation development, expertise and surveys |
2020 - 2021 |
Technical retrofitting of a 24 MW industrial boiler plant, Moscow |
JSC Plastics Institute |
Permits, surveys, working documentation development, expertise |
2017 – 2018 |
Technical retrofitting of a 35.0 MW combined steam and hot water boiler plant, Moscow |
JSC Salyut Gas Turbine Research and Production Center |
Working documentation development, field supervision |
2016 – 2019 |
10.5 MW hot water boiler plant for a residential complex, Moscow Region |
LLC Centro-Stroy |
Design and working documentation development, construction and installation works |
2016 – 2017 |