Good afternoon Please advise on the following issue: we applied for technical conditions for connecting to gas from the State Unitary Enterprise MO "Mosoblgaz" (we are gasifying an existing complex of warehouses in the Moscow region). Along with other documents, we were asked for a thermal engineering calculation. Tell me, how long does this calculation take to complete, and for what purpose is it required?
The question is answered by the Chief Project Engineer of Energia Plus LLC Zhizhina Egorovna
Thermal engineering calculation (otherwise calculation of heat and fuel) is actually the basis for considering your application for connection. Without this document, the gas supply organization (in this case Mosoblgaz) does not know how much heat and, accordingly, fuel your facility requires. Based on the calculated data, the gas supply organization searches for options for connection points to existing networks, taking into account the needs of your facility and existing consumers.
The thermal engineering calculation itself is a document certified by the contractor (most often a design organization) and containing calculation data with the calculation methodology used.
The preparation time for thermal engineering calculations is 1-3 weeks. The execution time depends on the scale of the facility, the state of the infrastructure and the completeness of the data provided by the customer company.